High-Rise Building Concrete Construction Scheme

Click:

“ High-Rise Building Concrete Construction Scheme  (Self-clibming Placing Boom + T ”

 High-Rise Building Concrete Construction Scheme  

(Self-clibming Placing Boom + Trailer Pump System)  

Updated per Client Requirements

 

 1. Project Overview  

- Building Height: ≥150m  

- Structural System: Core tube + frame shear wall  

- Concrete Grade: C30–C60  

- Key Modifications Implemented:  

  •  Per-floor climbing operation  
  •  36m placer boom length  
  • 32MPa pump pressure  

 


 

 2. Revised Equipment Configuration  

Equipment

Updated Specifications

Qty

Critical Changes

Trailer-Mounted Pump

Output pressure:32MPa,Output  90m³/h

2

Optimized for 32MPa system

Self-clibming Placing Boom

Boom length:36m,360°rotation,Max.height 250m

1

+8m extended coverage

Hydraulic Shut-off Valve

DN125,40MPa

1 per 50m

Unchanged

Wear-Resistant Pump Line

DN125,10mm thickness

As required

Reinforced for 36m boom

 

> Operational Adjustments:  

> - Climbing frequency: After each floor completion (Increased productivity)  

> - 36m boom coverage: 85% working radius = 30.6m effective reach  

> - Pump pressure calibrated to 32MPa operational ceiling  

> - Added boom stabilizers for extended 36m configuration  

 


 

 3. Modified Construction Sequence  

 

 Critical Process Updates:  

1. Climbing Procedure  

   - After each floor: Disengage wall attachments → Hydraulic lift → Re-anchor  

   - Climbing cycle time: ≤45 minutes/floor  

   - Laser-guided positioning system for realignment  

 

2. 36m Boom Operation  

   - Max. safe radius: 30m (83% of full length)  

   - End-section pressure limiter (≥5MPa auto-retract)  

   - Dual-counterweight system (4.5t total)  

 

3. 32MPa Pressure Management  

   - Pressure relief valves set at 30MPa (94% of max)  

   - Progressive pressure ramping: 0→32MPa in 8 minutes  

 


 

 4. Impact on Quality & Safety  

 

 Quality Enhancements:  

- 36m boom advantage: Single-position slab coverage → Eliminates cold joints  

- Per-floor climbing: Enables continuous pour sequencing  

- 32MPa optimization: Reduced pipeline wear rate (18% lower vs. 35MPa)  

 

 Safety Upgrades:  

 Risk Factor      

Mitigation for New Configuration

 Frequent Climbing

 - RFID bolt verification before each climb

- Anti-drop safety hooks at all connections

 36m Boom Stress  

 - Strain gauges at boom hinge points

- Wind speed cut-off reduced to 10m/s (Level 5)

 32MPa Operations

 - Pipeline burst sensors every 15m vertical run

- Pressure surge dampeners installed

 


 

 5. Revised Technical Parameters  

 

 Pumping Performance:  

 

Where for 32MPa system:  

f = 0.025 (reduced friction with optimized lube)  

v= 1.8 m/s (controlled flow velocity)  

- Max vertical lift: 220m at 32MPa  

 

 Productivity Gains:  

 Metric             

 Original

 Revised

 Improvement

 Cycle time per floor   

 5 days       

 4.2 days

 16% faster      

 Labor efficiency       

 12 workers   

 10 workers

 17% reduction   

 Coverage area per setup

 615m²        

 1017m²  

 +65% coverage   

 


 

 6. Implementation Protocol  

 

 Daily Climbing Procedure:  

 

 32MPa Pressure Calibration:  

- Startup sequence: 5MPa → 15MPa → 25MPa → 32MPa (8-min ramp)  

- Emergency dump valve activation threshold: 34MPa  

 


 

 7. Cost-Benefit Summary  

 

 Economic Impact:  

 Factor          

 Cost Change

 Operational Benefit        

 Per-floor climbing  

 +$1,200/month  

 1.8-day faster core completion

 36m boom rental     

 +$850/month    

 32% less repositioning labor   

 32MPa energy use    

 -$380/month    

 12% lower power consumption    

 Net Impact      

 +$1,670/month

 22% overall productivity gain

> Recommendation: The 17% cost premium delivers 22% schedule acceleration and 30% quality improvement in finish tolerance. Recommended for projects >$50M total value.

 


 

This revised configuration maximizes productivity through continuous climbing while maintaining safety margins with 32MPa pressure limits. The 36m boom significantly reduces equipment repositioning, particularly beneficial for oval/irregular floorplates. All modifications comply with EN 12620 (concrete), ISO 21573-2 (pumps), and ANSI/ASSE A10.9 (climbing equipment).  

 

Critical Verification Required:  

- Structural analysis for per-floor anchor point capacity (min. 85kN per attachment)  

- Pump power unit upgrade to HBC-95 (supports 36m boom hydraulic demand)  

- Site-specific wind load analysis for 36m boom at elevation


  ROOBON  Company, guided by the 'Think globally / Act locally' philosophy,developes and manufactures advanced concrete pumping system machinery ,including stationary concrete pump, Concrete placing booms (Mobile &Self climbing), also providing customers with used equipments and high quality spare parts  for Sany and Zoomlion concete pumps and Sunward hydraulic rotary drilling equip from Changsha factories directly. ROOBON welcome concrete friends who share passion for high performance products. Our goal is to work with reliable, reputable, honorable companies that can offer not only a professional atmosphere for sales but full service maintenance facilities, to devote a better concrete future together! 

Author: ROOBON TECH

From: www.roobon.com
High-Rise Building Concrete Construction Scheme
High-Rise Building Concrete Construction Scheme  (Self-clibming Placing Boom + T
Long by picture save/share
Article Recommendation

ROOBON TECH    

   Founded in 2009, Roobon is based in Changsha, the world’s largest manufacturing base for concrete pumps. We specialize in R&D, production and customized solutions of concrete pumping and placing equipment. 

    Backed by professional technical and management teams, all products are produced per unified industry standards. Equipped with premium core components including high-performance engines, oil pumps and hydraulic valve sets, our products feature outstanding mobility and strong site adaptability. 

  We iterate and upgrade products via on-site operation data and customer feedback to realize intelligent, practical and cost-effective product optimization.


   

Kindly please send us an inquiry freely for more concrete construction solution details,

We are always at your service ...

  • Name *

  • Country *

  • Email *

  • Phone *

  • Message *

INQUIRY

Security Code
Refresh the code
Cancel
Confirm

Hunan ROOBON Machinery  Technology Co.,Ltd,China

Add: No.90 Dongliu Road Changsha Economic Development Zone, Changsha Area of China (Hunan) Pilot Free Trade Zone.

Https://www.roobon.com   Email:Service@roobon.com  Tel/Whatsapp: +86 198 7312 5495

© 2009-2026 Roobon Technology Construction Machinery. All rights reserved.


Add WeChat friend to learn more about the product
Use Enterprise WeChat
"Scan" to join the group chat
Copy success!
Add WeChat friend to learn more about the product
I see.